Today's CRE AI Briefing: Oracle's Project Jupiter campus debt — about $18B in loans tied to the Doña Ana, New Mexico AI site — is quoted around 89–91 cents with syndication stalled (FT via Reuters), while power-path pressure continues after New Mexico blocked a supporting gas pipeline. Meanwhile the House passed the Ratepayer Protection Act 417–3, then the Senate blocked a quick unanimous-consent pass — cost allocation for large data-center loads is now a politics clock beside interconnection. And PGIM Real Estate sold a permitted 30 MW Munich-area development site, crystallizing planning and grid value. Underwrite the gate that starts rent, not just the megawatt headline.

Reach out to the AI Consulting Network: https://www.theaiconsultingnetwork.com/

Sources:

- Reuters (citing FT): https://www.reuters.com/business/finance/oracles-18-billion-data-center-debt-under-pressure-ft-reports-2026-09-18/

- Albuquerque Journal: https://www.abqjournal.com/news/land-commissioner-nixes-project-jupiter-pipeline-for-second-time/3083075

- Roll Call (House): https://rollcall.com/2026/09/16/bill-aimed-at-voter-anger-over-data-centers-passes-house/

- Roll Call (Senate): https://rollcall.com/2026/09/17/ratepayer-bill-aimed-at-data-center-buildout-blocked-in-senate/

- CNBC: https://www.cnbc.com/2026/09/17/ai-data-center-utility-cost-senate.html

- BeBeez: https://bebeez.eu/2026/09/18/pgim-sells-data-center-development-site-in-munich/

Tämä jakso on lisätty Podme-palveluun avoimen RSS-syötteen kautta eikä se ole Podmen omaa tuotantoa. Siksi jakso saattaa sisältää mainontaa.

Jaksot(254)

SoftBank: 9.75% Coupons Clear Oct 1 OpenAI Wire - CRE AI Briefing, Sep 28, 2026

SoftBank: 9.75% Coupons Clear Oct 1 OpenAI Wire - CRE AI Briefing, Sep 28, 2026

SoftBank cleared about $11.1 billion of senior notes with coupons up to 9.75% to fund its final $10 billion OpenAI tranche due October 1, as the 10-year Treasury sat near 5.17% and JPMorgan still maps...

28 Syys 1min

Lambda: $500M OK Taxes on AI Campus - CRE AI Briefing, Sep 27, 2026

Lambda: $500M OK Taxes on AI Campus - CRE AI Briefing, Sep 27, 2026

Lambda announced a new AI data center at MidAmerica Industrial Park in Mayes County, Oklahoma, with about $500 million in taxes over 10 years, up to 1,000 construction jobs, and a full ratepayer shiel...

27 Syys 1min

Nscale: $3.36B Convertible Pre-IPO for AI DC Buildout — CRE AI Briefing, Sep 26, 2026

Nscale: $3.36B Convertible Pre-IPO for AI DC Buildout — CRE AI Briefing, Sep 26, 2026

Nscale closed a $3.36 billion pre-IPO convertible led by Third Point, with $2.36 billion already funded and a $1 billion Nvidia commitment due mid-November, against more than $103 billion in contracte...

26 Syys 1min

Cipher: Barber Lake to $9B+ on 20-Year Lease — CRE AI Briefing, Sep 25, 2026

Cipher: Barber Lake to $9B+ on 20-Year Lease — CRE AI Briefing, Sep 25, 2026

Cipher stretched Barber Lake to a twenty-year contracted lease and lifted facility revenue from $3.8 billion to over $9 billion, with about $5.2 billion from a follow-on decade with a leading AI lab a...

25 Syys 1min

Oracle: Force Majeure on 2.45 GW Jupiter Lease — CRE AI Briefing, Sep 24, 2026

Oracle: Force Majeure on 2.45 GW Jupiter Lease — CRE AI Briefing, Sep 24, 2026

Oracle sent Blue Owl a force majeure notice on Project Jupiter, a 2.45 GW New Mexico Stargate campus aimed at 2028, seeking room to delay lease payments if COD slips while $18B of bank debt and $3B of...

24 Syys 1min

Anthropic: 1 GW Stream Talks, ~$40B Infra — CRE AI Briefing, Sep 23, 2026

Anthropic: 1 GW Stream Talks, ~$40B Infra — CRE AI Briefing, Sep 23, 2026

Today's CRE AI Briefing: Anthropic is in early talks to lease up to 1 GW directly from Apollo-backed Stream Data Centers — a footprint developers peg at about $40B of infrastructure, with Google credi...

23 Syys 1min

CoreWeave: $1.1B Bonds Back 76 MW, $2.94B 15-Year Lease — CRE AI Briefing, Sep 22, 2026

CoreWeave: $1.1B Bonds Back 76 MW, $2.94B 15-Year Lease — CRE AI Briefing, Sep 22, 2026

Today's CRE AI Briefing: Goldman-led banks kick off about $1.1 billion of high-yield notes for Blue Owl's Digital Drive near Richmond — 76 MW fully leased to CoreWeave under a 15-year, $2.94 billion c...

22 Syys 1min

CleanSpark: $2.28B Notes Back Meta's $6.6B 175 MW Lease — CRE AI Briefing, Sep 21, 2026

CleanSpark: $2.28B Notes Back Meta's $6.6B 175 MW Lease — CRE AI Briefing, Sep 21, 2026

CleanSpark priced about $2.276 billion of 7.875% senior secured notes due 2031 (at 98.5% of principal) to finish its Sandersville, Georgia data center — anchored by Meta’s 20-year, roughly $6.6 billio...

21 Syys 1min

Suosittua kategoriassa Politiikka ja uutiset

uutiscast
vallattomat
aikalisa
politiikan-puskaradio
rss-viihde-media
ootsa-kuullut-tasta-2
rss-ootsa-kuullut-tasta
rss-vaalirankkurit-podcast
otetaan-yhdet
tervo-halme
et-sa-noin-voi-sanoo-esittaa
rss-voi-venaja
rss-asiastudio
rss-raha-talous-ja-politiikka
the-ulkopolitist
rss-podme-livebox
rss-ulkopoditiikkaa
rss-girls-finish-f1rst
rss-kaikki-uusiksi
rss-seksicast